Radical Project
- January 27, 2005
No CommentsDeveloper: Radical Projects Pvt. Ltd. Total built-up area: 10,185 m2 Outcome: Energy savings of nearly 40 % compared to the base case 28% reduction in air-conditioning system... -
Smart GHAR III, Rajkot
- August 17, 2007
Developer: Rajkot Municipal Corporation Total Built-up area: 57,408 m2 Outcome: Peak temperatures reduced by ~5°C in bedrooms. Inside temperature will be equal or below 30°C for ~70%... -
P-17 Residential Project, Mahindra World City
- September 27, 2005
Developer: Mahindra Lifespace Developer Ltd. Total Built-up area: 1.19 lakh m2 Outcome: Peak temperatures reduced by ~4°C in bedrooms. Inside temperature will be equal or below... -
Advant Navis Business Park
- November 7, 2003
Developer: Advant IT Park Total Built-up area: 32,200 m2 Estimated energy savings: ~34% compared to original design... -
DB Pride
- September 9, 2007
Developer: DB Infrastructures Pvt. Ltd Total Built-up area: 2.3 lakh m2 Outcome: Peak temperature reduced by 7°C in worst orientated bedrooms. 66% energy savings ACs.... -
Avantika University
- September 9, 2007
Developer: MIT Group of Institutions Outcome: Improved thermal comfort in hostel blocks Estimated energy savings of ~30% in educational block compared to original design... -
Symbiosis University of Applied Sciences
- August 31, 2003
Developer: Symbiosis Foundation Total Built-up area: 11,555 m2 Outcome: Estimated energy savings of ~24% in management block compared to original design... -
Educational and Innovation Centre, Pune
- August 26, 2006
Developer: Gherzi Consulting Engineers Pvt. Ltd. Total Built-up area: 5,135 m2 Outcome: Estimated overall energy savings of ~44% compared to original design... -
Cereberum tower, Intellicity
- May 13, 2005
Developer: Airwill Group, Noida Total Built-up area: 64,559 m2 Outcome: Estimated energy savings of ~35% compared to original design... -
World Trade Centre, GIFT City
- April 30, 2004
Developer: SpireWorld Total Built-up area: 1 lakh m2 Outcome: Estimated energy savings of ~28% compared to ECBC compliant design...